2020 Street Resurfacing Project

2010 Resurfacing
Street Resurfacing
2020 Street Resurfacing Project Map Page 1
2020 Street Resurfacing Project Map Page 2

Overview

The Town of Carrboro maintains 46.61 miles of streets comprising of 566 street segments or blocks, 41 miles of sidewalks, and 872 curb ramps throughout the community. The 2020 Street Resurfacing Project is intended to keep the streets and curb ramps safe and in good condition for all users, and to make improvements strategically and efficiently to ensure safer and longer-lasting streets and curbs.

Project Description

Carrboro’s 2020 Street Resurfacing Project includes repairs and resurfacing to 3.57 miles of streets, 54 curb ramp replacements, installation of 41 curb ramp strips, and related construction activity such as manhole adjustments and pavement markings.  

Construction will begin the week of May 25th with curb ramp upgrades and utility adjustments. Street resurfacing will begin in July.  The project is expected to be completed by September.

Street Resurfacing Project Map

2020 Street Resurfacing Project Map (PDF)

Street List

StreetFromTo
Blocker RdShadow Ridge PlDead end
Camden LnGloucester CourtCul-de-sac
Camden LnHomestead RdGloucester Ct
Dairy CtLong Meadows RdDead end
Gloucester CtCamden LnCul-de-sac 
S. Fields CirLong Meadows RdLong Meadows Rd
High StGoldston DrW. Main St
High StCheswick CtGoldston Dr
High StHillsborough RdCheswick Ct
Hogan Glen CtLong Meadows RdCul-de-sac
Hogan Glen CtLong Meadows RdCul-de-sac
James StLorraine StCarol St
James StRainbow DrQuail Roost Dr
James StW Main StLorraine St
James StCarol StRainbow Dr
James StQuail Roost DrHillsborough Rd
Jasmine CtRobert Hunt DrCircle - CDS
John Martin CtRobert Hunt DrCircle - CDS
Lake Hogan Farm RdHomestead RdLake Hogan Ln
Lake Hogan Farm RdHogan Woods CirCommons Way Dr
Lake Hogan Farm RdLake Manor RdHogan Woods Cir
Lake Hogan Farm RdLake Hogan LnLake Manor Rd
Long Meadows RdHogan Glen CtHogan Ridge Ct
Long Meadows RdHogan Ridge CtDairy Glen Rd
Long Meadows RdBay View DrHogan Glen Ct
Long Meadows RdDairy Glen RdHogan Hills Rd
Lorraine StMelba CirMary St
Lorraine StPhipps StMelba Cir
Lorraine StCarol StPhipps St
Lorraine StMary StJames St
Lorraine StHillsborough RdCarol St
Melba CirLorraine StCul-de-sac
Robert Hunt DrN Greensboro StJasmine Ct
Robert Hunt DrJasmine CtJohn Martin Ct
Shadow Ridge PlLong Meadows RdBlocker Rd
Shadow Ridge PlBlocker RdCul-de-sac
W Poplar AveOld Fayetteville RdHighway 54

Notices Prior to Construction Activity

One week before construction activity begins, the Contractor shall install advance warning signs for the Project.

48 hours prior to resurfacing activities, notices will be placed on vehicle windshields parked on the street announcing the upcoming street resurfacing activities and that owners should move their vehicle from the street.  

During resurfacing

  • Please observe all signage and flaggers.
  • Be aware of all workers and equipment in the street and please drive slowly and carefully.  
  • Please do not park on street until work is complete and your entire road has been paved and stripped. If you cannot avoid parking on the street please be prepared to move your vehicle upon request when work is being preformed on your street.  
  • Please keep yard debris out of street/curb.  

Residents may be inconvenienced by the project work. We apologize for any inconvenience and appreciate your patience and cooperation during the period of improvement.

Questions

If you have any questions related to the project, please contact Public Works Department at (919) 918-7425 or email pworks@townofcarrboro.org